Work is still ongoing everyday, to deliver top-notch infrastructure, in the city. To ensure the completion of the key roads during the dry spell of October – December, complete with the standard storm water drainage, they have started industrial-scale production and stock- piling of precast concrete for the drains, aggregates, sand and other materials in our Construction Yard. Also, the second Monument Gate on the main AMC Avenue, and the Exit Area fencing are work-in-progress
|