COREN approves Gombe Assembly Complex Project

COREN moves to give engineering qualifications Int'l recognition

The Council for the Regulation of Engineering in Nigeria (COREN) has approved the resumption of work at the Gombe State House of Assembly complex project.

The development followed the conclusion of an investigation by the council into the collapse of the reinforced concrete entrance canopy.

It will ​‌‌‍⁠‌‍⁠⁠‍​​​‍‍‍‌‍‌​be recalled that the canopy collapsed on July 24, when fresh concrete was being placed on the structure.

Prof. Okorie Uche, National Registrar, COREN, said this while presenting the report of the investigative panel on Saturday in Gombe.

Uche said that the investigation established that the consulting structural engineer engaged on the project was qualified but failed to engage registered professionals, including engineers and architects.

He said findings showed that while the structural designs were checked and sealed by the consulting engineer, the working drawings had not been approved by the relevant state authorities.

The official said tests conducted on the concrete and reinforcement indicated that the standing structure was technically adequate.

“The panel identified deficiencies in the temporary formwork and construction sequence as possible factors responsible for the collapse.

“The findings revealed that the concrete was cast at once rather than in stages,” he said.

Uche said that the panel based on its findings recommended continuation of construction work subject to adequate supervision by qualified professionals.

Receiving the report, Manassah Jatau, the state deputy governor, commended the panel for a thorough investigation and assured implementation of its recommendations.

Jatau said that anyone found responsible for the incident would be held accountable.

He said that work on the project would resume under strict professional supervisions.

Also, Isyaka Lawal, Chairman of the panel, said that the investigation lasted for two months due to the time required to evacuate debris from the collapsed structure.

He said that the report would prevent a recurrence and strengthen professional standards in the execution of projects in the state.